Work nears completion on De Rosee Sa’s £450k Hammersmith home

  • Comment

Construction is nearing completion on a house designed by De Rosee Sa on the site of a former garage in Hammersmith, West London 

PROJECT DATA

The £450,000 scheme will replace the ageing structure which sat in between terraced gardens and a row of 16 garages.

The owners live across the road and had originally bought the awkward site to prevent it from being developed but have now decided to build a house on it themselves.

The two-bedroom house is just a single storey above ground due to planning restrictions and features a basement level to provide extra accommodation space.

There was also a restriction on placing windows in the boundary wall so a pair of atria bring light into courtyard spaces within the 132m2 building. 

The scheme is expected to complete later this summer. 

Hammersmith house by De Rosee Sa

Hammersmith house by De Rosee Sa

Project data

Location Hammersmith
Type of project residential
Client private
Architect De Rosee Sa
Structural engineer BCS Consulting
Main contractor PPBS
Appointment word of mouth
Tender date January 2015
Start on site date June 2015
Completion date Summer 2016
Contract duration 12 months
Gross internal floor area 132m2
Form of contract and/or procurement JCT ICD Contract
Contract value £450,000

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.