Unsupported browser

For a better experience please update your browser to its latest version.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Full extent of construction failures on evacuated Sydney tower revealed 

Shutterstock opal tower in january 2018
  • 2 Comments

Under-designed beams, partially grouted joints and construction and material deficiencies were responsible for the damage to the evacuated A$165 million (£91million) Opal tower in Sydney, Australia, a final independent report has found.

It found a number of problems with the design and construction of the reinforced concrete building, which has post-tensioned concrete floors. The tower, designed by architect Bates Smart, was completed in August last year.

According to AJ sister publication New Civil Engineer, the report was carried out by consultant Unisearch. 

The 36-storey tower was evacuated on Christmas Eve last year after large cracks appeared on the 10th floor. Engineers then discovered more cracks on the fourth floor and temporary props were installed as a precaution. The tower has remained unoccupied since. 

The cracks were found in the precast panels and their supporting ‘hob’ beams, which clad the six-storey tall inset slots that form a feature of the building.

The report concludes that the as-constructed hob beams and panel assembly were ‘under-designed’ according to the National Construction Code (NCC) and the Australian Standard for concrete structures (AS3600) at a number of locations in the building. This, it says, left the beams susceptible to failure by shear compression and bursting.

It also concludes that the decision to only partially grout the joints between the hob beams and panels, ‘significantly raised the levels of stress’ in the hob beams on floors 4, 10, 16 and 26. This decision was taken after the initial design was completed.

‘Only inner surfaces, of approximately 50 per cent to 70 per cent of the joint width, appear to have been grouted, consistent with the shop drawings which show the grout extending over only the inner portion of the hob beam to panel connection,’ the report states.

‘Furthermore, coring of the level four hob beam revealed incomplete grout coverage in some places. This partial grout coverage led to an eccentric bearing load and elevated bearing and bursting stresses on the hob beams.’

Construction and material deficiencies ‘likely precipitated’ the cracking on level 10 where an electrical conduit and reinforcing steel were in the cover region of the concrete and where there had been a panel repair, says the report.

On the fourth floor, lower-strength concrete and the partial grout coverage had contributed to the failure of the beam.

‘Test records of materials used in construction revealed at least one case where concrete used in a hob beam may not have reached its specified 28 day strength,’ it adds.

Opal tower damaged hob beam on level 4 after concrete removed

Opal tower damaged hob beam on level 4 after concrete removed

Opal tower- damaged hob beam on level 4 after concrete removed

Incomplete dowel bars, inadequate concrete cover and potentially inadequate tensile capacity in the horizontal direction in one of the panels were also listed as where construction had been different from the design or the standards.

Unisearch said it had drawn the conclusions after a number of activities including multiple inspections, reviews of the construction records, security camera footage and design documents.

The tower was designed with structural engineers WSP and built by contractor Icon.

An interim report into the cause of the damage was published in January. It said that despite the damage, the building was ‘overall structurally sound’. The new report said it found no evidence to contradict this.

Unisearch said it had not received complete details of the structural analysis for the proposed repairs to strengthen the structure and recommended that detailed plans should be checked by an independent engineer. But it said the structural principles behind the proposal were ‘sound’.

WSP and Icon have been contacted for comment. 

Opal tower damaged hob beam on level 4 before concrete removed

Opal tower damaged hob beam on level 4 before concrete removed

Opal tower - damaged

  • 2 Comments

Readers' comments (2)

  • If anyone thinks that this sort of thing couldn't happen in Britain, just look at the Edinburgh schools scandal.

    Unsuitable or offensive? Report this comment

  • Industry Professional

    A factor seems to be a late decision to grout only partially. It all goes to show how the design change process needs to be properly understood by all involved with any changes.
    Sometimes it can be because people just do not realise the significance of a change, sometimes because key people are no longer involved (they have left or whatever) and sometimes it is because people think "it will be alright".
    Personally, I am all for clerk of works' inspections and also for designers to be involved all the way through and not to be put into tightly controlled boxes by people who should know better.

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.

Related Jobs

AJ Jobs