ST GILES BUILDINGS, NEWLAND PARK

  • Comment

Cost analysis

SUBSTRUCTURE FOUNDATIONS/SLABS £24/m2

Traditional in-situ concrete trench-fill foundations, brick foundation walls, precast-concrete beam-and-block floors

SUPERSTRUCTURE FRAME £7/m2

Partial steel frame in support of bay windows

UPPER FLOORS £14/m2

Precast-concrete beam-and-block floors

ROOF £24/m2

Main roofs - prefabricated timber trusses, felt and slates. Flat roofs - lead-covered timber construction

STAIRCASES £26/m2

External access stairs in galvanised steel with Welland Multipanel galvanised treads and landings

EXTERNAL WALLS £62/m2

Loadbearing traditional facebrick-and-block insulated cavity walls with cedar-clad feature panels

WINDOWS £24/m2

Aluminium powder-coated double-glazed units

EXTERNAL DOORS £8/m2

Solid-core flush doors, paint finish

INTERNAL WALLS AND PARTITIONS £35/m2

Lightweight blockwork

INTERNAL DOORS£17/m2

Flush doors, paint finish

INTERNAL FINISHES WALL FINISHES £17/m2

Plaster with emulsion finish, partial wall tiling

FLOOR FINISHES £25/m2

Screed with carpet finish, screed with vinyl finish to kitchen and bathroom areas

CEILING FINISHES£9/m2

Plasterboard with emulsion finish

FITTINGS AND FURNISHINGS FURNITURE £43/m2

Fitted kitchens, freestanding bedroom furniture

SERVICES SANITARY APPLIANCES £18/m2

SERVICES EQUIPMENT £5/m2

upvc soil and wastes, intumescent fire stopping between floors

WATER INSTALLATIONS & SPACE HEATING £73/m2

Traditional hot and cold water systems, gas-fired localised boilers serving radiators

ELECTRICAL SERVICES £74/m2

Includes external lighting, fire-alarm and telecom installations

BUILDER'S WORK IN CONNECTION £2/m2

PRELIMINARIES AND INSURANCES PRELIMINARIES, OVERHEADS AND PROFITS £89/m2

EXTERNAL WORKS LANDSCAPING/WORK IN PUBLIC HIGHWAY £36/m2

PROVISIONAL SUMS, CONTINGENCIES AND DAYWORK £38/m2

Cost summary

Cost per m2 Per cent(£)of total

SUBSTRUCTURE243.6

SUPERSTRUCTURE

Frame71.0

Upper floors142.1

Roof243.6

Staircases263.9

External walls629.3

Windows243.6

External doors81.2

Internal walls and partitions355.2

Internal doors172.5

Group element total21732.4

INTERNAL FINISHES

Wall finishes172.5

Floor finishes253.7

Ceiling finishes91.3

Group element total517.5

FITTINGS AND FURNISHINGS 436.4

SERVICES

Sanitary appliances182.7

Disposal installations50.8

Water installations and heating7310.9

Electrical services7411.0

Builder's work in connection20.3

Group element total17225.7

EXTERNAL WORKS AND DRAINAGE365.4

PROVISIONAL SUMS385.7

PRELIMINARIES AND INSURANCE8913.3

Total670100.00

CREDITS

CONTRACT TYPE JCT 80

START DATE 8 August 1996

COMPLETION DATE 19 February 1998

GROSS FLOOR AREA 6706m2

TOTAL COST £4,950,000

CLIENT Buckinghamshire Chilterns University College

ARCHITECT Corrigan+ Soundy+Kilaiditi

QUANTITY SURVEYOR Gleeds

STRUCTURAL ENGINEER Young & Webb

SERVICES ENGINEER mec Bird Associates

MAIN CONTRACTOR Ballast Wiltshier

SUBCONTRACTORS AND SUPPLIERS landscaping Linden Landscapes, wet-area landscaping Hillier Landscapes, steel staircases Hubbard Architectural Metalwork, windows Schuco International, bricks (Hamil Multi & Dorchester Red) James & Taylor, furniture oed, kitchens Moons Furniture Group, signs Shrimpton Signs, ironmongery James Gibbon Format, sign bollards Foxhall Engineering, roof trusses Crendon Timber Engineering, pre-cast floors Marshalls Flooring, drainage Hepworth Building Products, tanking and dpcs Marley Waterproofing, roof slates Eternit uk, carpets Interface Europe, pvc sheeting Altro, loft insulation Warmcel, curtains Bruce & Lumb, external lights Beta Lighting, roofing Court Roofing, doors Nationwide Joinery

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.