Piercy & Co finishes ‘pared-back’ Bloomsbury townhouses

  • Comment

Piercy & Company – formerly Piercy Conner Architects – has completed this £1.4 million, three-townhouse scheme in the Bloomsbury Conservation Area

The project for Great Marlborough Estates features ‘heavily textured masonry and detailed stone cills, lintels and stringer courses’.

The new townhouses in Wakefield, which won planning permission in spring 2010 (AJ 05.06.2010), are among the first to be built in the central London area for more than 75 years.

Piercy & Company’s Stuart Piercy said: ‘The site presented many issues with a beautiful Grade II*-listed garden and listed buildings to all sides - so it was very sensitive with an extremely vocal residents group. The key was to introduce a finer grain to the facade interpreting motifs from the conservation area in a contemporary language, while on the inside the opposite is true - we wanted large volumes of flexible light filled engaging spaces.

‘For me the project’s success is that the spaces feel light and generous while the houses sit very gently in the context of the 300 year old gardens.’

 

Project data

Architects: Piercy & Company
Location: Wakefield Street, Bloomsbury, London
Type Of Project: Three Private Town Houses
Structural Engineers: Pringuer-James Consulting Engineers
Project Architect: Henry Humphreys
Design Team: Henry Humphreys, Stuart Piercy, Susan Carruth, Stephanie Wilkins
Client: Great Marlborough Estates
Funding: Private
Tender date: N/A
Start on site date:
February 2011
Contract duration: 15 Months
Gross internal floor area: House A: 182.9m²; House B: 180.3m²; House C: 175.0m²
Form of contract and/or procurement: Single Stage Design & Build
Total cost: approx £1.4million    
M&e consultant: Martin Design Associates
Quantity surveyor: Paragon
Planning supervisor: RPS Planning
Lighting consultant: N/A
Main contractor: Forcia
Selected subcontractors and suppliers: Wienerberger (Brick Manufacturer) Porcelonsa (Tiles & Bathrooms) Force 05 (Stairs)
Annual co2 emissions: Approximately CSH 03

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.

Related Jobs

ARCHITECTURE JOBS BY EMAIL

Do you want the latest jobs emailed to you?
Sign up for job alerts.

AJ Jobs