Costs: office fit-out

  • Comment

Davis Langdon & Everest provides indicative costs for common items of work associated with office fitting-out. The rates are current at December 2002 and reflect competitively tendered work in the outer London area. Inner London rates may be up to 10 per cent higher while costs in the regions will generally be lower. The costs are indicative of those found on medium to large fit-out projects (more than 2,500m 2floor area). Smaller schemes will attract a premium to these rates

PARTITIONS Unit Range (£) Metal stud partitions one layer plasterboard both sides m 90-120 two layers plasterboard both sides; insulation m 120-170 two layers high-density core plasterboard;

acoustic insulation m 190-220 extra for curved work m 90-120 Demountable partitions frame with plasterboard m 190-210 frame and hung panel system m 200-220 extra for part-glazed panel m 150-210 Fully demountable 'monobloc' partitions solid wall m 220-350 single-glazed office front m 250-350 single-glazed office front - etched m 560+ double-glazed office front, interstitial blinds m 530-670 double-glazed office front - etched m 800+ Glazed partitions framed double-glazed partition m 660-720 frameless glazing m 690-730 fire-rated screen, 30/30, single-glazed m 890-1,000 fire-resisting security partition; including allowances for doors etc 30/30 insulation and integrity m up to 1,900 60/60 insulation and integrity m up to 3,200 120/120 insulation and integrity m up to 5,000

WALL FINISHES Panelling timber panelling m 2340-390 fabric-covered framed panelling m 2240+ acoustic panelling m 2380+ Dry lining dry wall dry lining and emulsion m 217-22 dry wall dry lining on M/F firrings; emulsion m 221-27 Stone cladding marble cladding m 2215-270 limestone cladding m 2340-500 granite cladding m 2340-560 Ceramic tiling ceramic tiling (kitchen/wash areas) m 247-57 ceramic tiling to public areas m 252-77 extra for render backing m 211-14 Hygienic finishes anti-bacterial paint finish m 227-32 PVC lining, 2.5mm m 252-62 laminate panel m 275-90 Applied finishes plaster and emulsion m 214-20 vinyl wall coverings m 212-20 high-quality vinyl wall covering m 222-32 fabric wall covering m 222-48 polished plaster m 2110-135

FLOOR FINISHES (SEE AJ FOCUS DECEMBER 2000) Raised floors light 100-300 cavity m 228-35 medium 150 cavity m 230-40 medium over 300 cavity m 235-50 heavy duty, 100-300 cavity m 245-55 extra for bonded sheet tile m 222-25 protection to floor tiles m 22-3 taking up and storing tiles m 210-15 Cavity barriers half-hour fire resistance; 100-200 cavity m 10-11 one-hour fire resistance; 100-200 cavity m 13-14 half-hour fire resistance; 300-400 cavity m 17-20 Acoustic barriers 100-200 cavity m 11-14

CEILING FINISHES Jointless plasterboard plasterboard on M/F system m 225-35 two layers plasterboard on M/F system m 230-40 moisture-resistant plasterboard on M/F system m 245-60 fibrous plaster feature suspended ceiling m 2125-190 Fibre tiles mineral fibre tiles; plain; exposed grid m 218-23 mineral fibre tiles; acoustic; exposed grid m 225-30 compressed rockwool; acoustic tile; concealed grid m 230-35 resin-bonded glasswool tile; plain;

semi-concealed grid m 237-42 high-density mineral fibre tile; exposed, anti-corrosive grid m 242-47 glass-reinforced gypsum ceiling tiles; plain; semi-concealed grid m 242-52 Metal tiles non-perforated metal tile suspended ceiling m 228-40 non-perforated metal tile suspended ceiling; moisture resistant m 240-55 perforated metal tile; lay-in grid m 235-50 perforated metal tile; demountable; concealed grid m 242-65 perforated metal tile; hinge access;

concealed grid m 248-68 perforated metal tile; demountable; linear grid m 255-67 perforated acoustic quality metal tile; hinge access mega-panel; tartan grid m 275-100 taking down and storing tiles m 210-12 fire barrier m 30-35 acoustic barrier m 30-40

FIXTURES AND FITTINGS Blinds venetian blinds, cord operated m 225-30 cloth blind, aluminium head, sides and channels, electrically operated m 2250-350 Kitchen units stainless-steel wash hand basin unit 43-60 stainless-steel sink unit, single bowl unit 380-430 stainless-steel sink unit, double bowl unit 500-590

FURNITURE The following costs include desk, pedestal, chair and storage Economic quality secretarial/admin unit 800-1,050 manager unit 1,250-1,500 executive unit 1,700-2,000 Mid-range quality secretarial/admin unit 1,250-1,600 manager unit 1,700-200 executive unit 2,300-2,850 High quality secretarial/admin unit 1,600-1,950 manager unit 2,150-2,400 executive unit 3,400+

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.