Cost comment

  • Comment
aj - building study

The building elements of the Challenger Learning Centre were let as two separate contracts.

The supply and erection of the prefabricated building units, including the provision of internal partitions and finishes: the installation of services and the completion of external works. These works were undertaken by S Wernick & Sons under a jct Intermediate Form of Contract 98 with amendments to incorporate elements of detail design responsibility.

The supply and erection of the external cladding shell consisting of steel trusses and tensioned pvc-coated polyester fabric. These works were undertaken by Aura Fabric Engineering under a jct Intermediate Form of Contract 98 with amendments to incorporate structural design responsibility.

In both of the contracts a sectional completion supplement was incorporated, so that in Spring 2001, some 15 months after the completion of the building at the Leicester University site, the contractors will return to dismantle the building and re-erect it adjacent to the newly completed nssc.

The design consultant for the building works was Nicholas Grimshaw & Partners with commercial management and project management undertaken by Capita Property Services and Gardiner & Theobald Management Services respectively. Throughout design and construction the project was characterised by positive teamwork, with all parties adopting a co-operative approach to resolve problems quickly and amicably. It is regarded as an outstanding success by the client and all those associated with it.

George Taft, Capita Property Services

Costs

Costs based on approximate proposed interim final account figures for both building contracts (Aura and Wernick) for the section completion of the building. Costs do not include costs for moving building to final site in Spring 2001.

SUBSTRUCTURE

FOUNDATIONS/SLABS £40/m2

Levelling site, oversite, cube foundations to prefab units and strip foundations to external cladding structure

SUPERSTRUCTURE

FRAME/PREFABRICATED UNITS £130/m2

Includes roof

EXTERNAL SHELL/CLADDING £240/m2

Steel frame trusses, all fittings and stretched fabric incorporating graphics

WINDOWS £50/m2

Shopfront glazing and film-applied graphics

EXTERNAL DOORS £10/m2

INTERNAL WALLS AND PARTITIONS £20/m2

Internal partitions incorporated into the pre-delivered prefabricated units

INTERNAL DOORS £10/m2

INTERNAL FINISHES

WALL FINISHES £5/m2

FLOOR FINISHES £35/m2

CEILING FINISHES £30/m2

FITTINGS AND FURNISHINGS

FURNITURE £5/m2

Most fittings and furnishings, including that to the 'Labryinth' and the reception area, were provided outside the building contract

SERVICES

SANITARY APPLIANCES £15/m2

Sanitary fittings

DISPOSAL INSTALLATIONS £10/m2

Soil waste and vent drainage, rainwater installation

WATER INSTALLATIONS £10/m2

Hot, cold and main water installation

SPACE HEATING AND AIR TREATMENT £65/m2

ELECTRICAL SERVICES £70/m2

PROTECTIVE INSTALLATIONS £35/m2

COMMUNICATION INSTALLATIONS £10/m2

BUILDERS' WORK IN CONNECTION £10/m2

PRELIMINARIES AND INSURANCES

PRELIMINARIES, OVERHEADS AND PROFIT £100/m2

EXTERNAL WORKS

LANDSCAPING, ANCILLARY BUILDINGS £22,000

Entrance ramp infill and tarmac path, topsoiling,

turfing and hedging, flagstaffs and banners

nners

cost summary

Cost per m2 Per cent

(£) of total

SUBSTRUCTURE 40 4.44

SUPERSTRUCTURE

Frame (including roof) 130 14.44

External shell/cladding 240 26.67

Windows 50 5.56

External doors 10 1.11

Internal walls and partitions 20 2.22

Internal doors 10 1.11

GROUP ELEMENT TOTAL 460 51.11

INTERNAL FINISHES

Wall finishes 5 0.56

Floor finishes 35 3.89

Ceiling finishes 30 3.33

GROUP ELEMENT TOTAL 70 7.78

FITTINGS AND FURNISHINGS 5 0.56

SERVICES

Sanitary appliances 15 1.67

Disposal installations 10 1.11

Water installations 10 1.11

Space heating and air treatment 65 7.22

Electrical services 70 7.78

Protective installations 35 3.89

Communication installations 10 1.11

Builders' work in connection 10 1.11

GROUP ELEMENT TOTAL 225 25.00

PRELIMINARIES 100 11.11

TOTAL 900 100.00

Costs supplied by George Taft, Capita Property Services

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.

Related Jobs