cost analysis

  • Comment

Costs based on tender sum

DEMOLITION

DEMOLITION £115,332

SUBSTRUCTURE

FOUNDATION/SLABS £92/m2

Piled

FRAME £80/m2

Steel

UPPER FLOORS £19/m2

Precast concrete

ROOF £51/m2

Flat with Anderson covering

ROOFLIGHTS £17/m2

STAIRCASES £42/m2

EXTERNAL WALLS £74/m2

Combination of Sto rendered blockwork and terracotta tiles WINDOWS AND EXTERNAL DOORS £38/m2

INTERNAL WALLS AND PARTITIONS £24/m2

INTERNAL DOORS £12/m2

INTERNAL FINISHES

WALL FINISHES £24/m2

FLOOR FINISHES £57/m2

CEILING FINISHES £11/m2

FITTINGS AND FURNISHINGS

FURNITURE £104/m2

SERVICES

SANITARY APPLIANCES £2/m2

SERVICES EQUIPMENT £90/m2

DISPOSAL INSTALLATIONS £24/m2

WATER INSTALLATIONS £39/m2

SPACE HEATING/AIR TREATMENT £145/m2

ELECTRICAL SERVICES £91/m2

LIFT AND CONVEYOR INSTALLATIONS £9/m2

PROTECTIVE INSTALLATIONS £20/m2

COMMUNICATION INSTALLATIONS £1/m2

BUILDERS' WORK IN CONNECTION £13/m2

PRELIMINARIES

PRELIMINARIES, OVERHEADS AND PROFIT £175/m2

EXTERNAL WORKS

LANDSCAPING, ANCILLARY BUILDINGS £376,192

cost summary

Cost per m2 Per cent

(£) of total

SUBSTRUCTURE 92 7.34

SUPERSTRUCTURE

Frame 80 6.38

Upper floors 19 1.51

Roof 51 4.07

Rooflights 17 1.36

Staircases 42 3.35

External walls 74 5.90

Windows and external doors 38 3.03

Internal walls and partitions 24 1.91

Internal doors 12 0.96

GROUP ELEMENT TOTAL 357 28.47

INTERNAL FINISHES

Wall finishes 24 1.91

Floor finishes 57 4.55

Ceiling finishes 11 0.88

GROUP ELEMENT TOTAL 92 7.34

FITTINGS AND FURNISHINGS 104 8.29

SERVICES

Sanitary appliances 2 0.16

Services equipment 90 7.18

Disposal installations 24 1.91

Water installations 39 3.11

Space heating/air treatment 145 11.56

Electrical services 91 7.26

Lift and conveyor installations 9 0.72

Protective installations 20 1.59

Communication installations 1 0.08

Builders' work in connection 13 1.04

GROUP ELEMENT TOTAL 434 34.61

PRELIMINARIES 175 13.95

TOTAL 1254 100.00

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.