Unsupported browser

For a better experience please update your browser to its latest version.

Your browser appears to have cookies disabled. For the best experience of this website, please enable cookies in your browser

We'll assume we have your consent to use cookies, for example so you won't need to log in each time you visit our site.
Learn more

Revealed: Grimshaw and Carillion coughed up £7m over Bath Spa

  • Comment

Grimshaw and contractor Carillion paid Bath & North East Somerset Council (B&NES) nearly £7million in settlement of the Thermae Bath Spa project dispute

The exact amount of the out-of-court deal, made last November to avoid a High Court showdown, had not initially been disclosed. However the local news paper has uncovered figures showing the pair will eventually pay £6.962 million in compensation to the authority on the £45 million scheme which opened five years late and almost two-and-a-half times over budget.

A £21 million claim by the council against main contractor Carillion was expected to go to court in January 2010.

Carillion had originally sought £2.4 million from the council after contractor Mowlem, which was bought by the company in 2007, was kicked off the job in 2005 following a series of construction defects. Grimshaw was dragged into the dispute as a third party in late 2008, when the council launched the huge counterclaim.

Previous story: 18 November 2009

Grimshaw reaches settlement with council over spa dispute

Nicholas Grimshaw & Partners, now known as Grimshaw, has avoided a High Court showdown after agreeing to pay an undisclosed sum to Bath & North East Somerset Council (B&NES) towards settlement of the Thermae Bath Spa project dispute

The council’s £21 million claim against main contractor Carillion was expected to go to court in January 2010. Carillion originally sought £2.4 million from the council after contractor Mowlem, which was bought by the company in 2007, was kicked off the job in 2005 following a series of construction defects. 

This latest move effectively ends almost two years of litigation. Grimshaw was dragged into the dispute as a third party in late 2008, when the council launched a counterclaim, saying it had ‘suffered loss and damage which it [was] entitled to recover […] from Nicholas Grimshaw for paint and waterproofing defects, design defects and a failure to carry out adequate tests’.

Thermae Bath Spa (pictured) opened in 2006 – five years late and almost two-and-a-half times over budget, at £45 million.

In an interview with the AJ in 2006, Grimshaw director Mark Middleton admitted that ‘mistakes had been made’, but he added: ‘The building we wanted has been built.’

A statement released by Grimshaw this week said: ‘We are pleased that a settlement has been concluded and proud that our vision for Thermae Bath Spa has proven to be a big success with residents and visitors of Bath alike.’

Timeline:

March 1997 – Grimshaw wins £19 million spa competition

August 2000 – Mowlem appointed contractor. Spa due to open 2002

September 2000 – work starts

August 2006 – spa opens

Summer 2008 – Carillion claims £2.4 million from B&NES

December 2008 – B&NES counterclaims £21 million

November 2009 – Out-of-court settlement reached with Carillion and Grimshaw, agreeing to cover B&NES net payments

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.

Related Jobs

AJ Jobs