Associated Architects completes gateway to Birmingham City University

  • Comment

Associated Architects has completed the second phase of Birmingham City University’s Curzon Street campus 

ARCHITECT’S VIEW • PROJECT DATA

The £46.2million building, which sits on the eastern axis of Patel Taylor’s Eastside City Park, has been designed to act as a gateway to the campus. 

The 23,238m2 scheme acts as a student hub and includes a central library, student services, students’ union, and cafes and restaurants. 

It also provides additional teaching space for the university’s education, law and social science, and business school departments. 

The practice has also recently been granted planning for the next phase of work at the university which is set to start in Spring 2016. 

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

Architect’s view 

The building has a clear University imprint; designed to be open and transparent to share its life with the adjacent park and streets. It is conceived as two wings of accommodation with six storeys on Curzon Street and five storeys following Cardigan Street, linked by an atrium on the axis of the ‘promenade’ running along the north of the park. Materials provide a modern update on the heritage of the area and echo those used elsewhere on the University estate, using render and brickwork with feature terracotta coloured fins to provide solar shading. 

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

Project data 

Location Birmingham
Type of project higher education
Client Birmingham City University
Architect Associated Architects
Landscape architect Atkins
Planning consultant Savills
Structural engineer White Young Green
M&E consultant Hoare Lea
Quantity surveyor Faithful & Gould
Planning supervisor Faithful & Gould
Lighting consultant Hoare Lea
Main contractor Wilmott Dixon Construction
Funding BCU
Tender date October 2012
Start on site date April 2013
Completion date September 2015
Contract duration 4 years, 1 month
Gross internal floor area 23,238m2
Form of contract and/or procurement Modified Design and Build contract / 2 stage tender
Total cost £46.2million

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

Birmingham City University’s Curzon Street Gateway Building by Associated Architects

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.

Related Jobs

AJ Jobs