Bennetts Associates' Camden Council offices on track for BREEAM Outstanding

  • Comment

New 13-storey building at King’s Cross aims to cut carbon emissions of Camden Council’s offices by 64 per cent

Designed by Bennetts Associates the new public building for Camden Council contains a range of facilities including a swimming pool, library, customer care centre, cafe and office accommodation.

The building has achieved BREEAM Outstanding during its interim design stage assessment and is due for completion in 2014. Strategies such as integration of green features in the structure, angled cladding for solar shading and an energy-efficient hybrid ventilation system helped attain the rating. Site-wide CHP provides heat to the building, while also displacing a significant proportion of the building’s electrical load.

During warmer months, the building is ventilated by a displacement system in the floor and night-time ventilation.

By balancing solar gain and increasing daylight penetration the building reduces its energy demand. The façade has been designed to provide adequate shading whilst improving aesthetics. The south-west and north-west facades consist of angled sections providing depth to the vertical reveals of the cladding. The windows of the south-east and north-east facades get progressively larger in the lower floors of the building to offset the reduced daylight levels caused by shade from adjacent buildings.

The council aims to both fund the project and reduce carbon emissions through selling old inefficient accommodation and relocating to the new site. Current energy costs suggest an annual saving of over £500,000 alongside carbon emissions 50 per cent lower than 2010 building regulations levels. The estimated savings have been calculated by comparing the predicted emissions of the new building to the emissions of the 11 Camden Council properties which will be vacated when staff is relocated to the King’s Cross building.

4

Project data

Start on site date: November 2011
Estimated completion date: Spring 2014
Net internal floor area: 17,200m2
Form of contract: Design and Build
Total cost: £65million
Target air tightness:  <5.0m³/hr/m²
Wall u-values: <0.2 W/m²K
Floor u-values: <0.15 W/m²K
Roof u-values: <0.15 W/m²K 
Glazing u-values: <1.4 W/.m²K
Electricity off-set by roof mounted PV: 2 per cent of total load
Electricity off-set by site wide CHP: 27 per cent of total load

Design team

Architects: Bennetts Associates
Structural engineer: AKT II

Services Engineer: Grontmij
Quantity surveyor: Davis Langdon 
Main contractor: Kier Build

See more Bennetts Associates’ projects in AJ Buildings Library.

Should RIBA have an annual sustainability award?

Vote in the AJ poll


Subscribe to Footprint by email and follow Hattie Hartman on twitter.

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.