Grimshaw team picked for £1bn Northern Line job

  • 2 Comments

Grimshaw has won the race to design the huge £1billion Northern Line extension, including new underground stations at Battersea Power Station and Nine Elms

The practice, which is already working on the massive HS2 and Crossrail projects, is part of the Ferrovial/Laing O’Rourke joint venture which has been named preferred bidder for the six-year contract.

It is understood Grimshaw, which increased its turnover by 44 per cent to £24 million according to its latest trading figures (AJ 07.01.14), will need to take on about 40 extra staff by the start of next year to handle the job.

Grimshaw and engineer Mott MacDonald are drawing up designs for all the station work, including the platforms and over-site developments. 

The team beat three other rivals: Bam Nuttall and Balfour Beatty with CH2M Hill (formerly known as Halcrow), Buro Happold and Acanthus Architects LW; Bechtel and Strabag with Arup; and Costain, Dragados and Sir Robert McAlpine with Atkins and Weston Williamson.

The proposed start of construction for the Northern line extension is spring 2015. Subject to funding and permission to build and operate the extension, the new stations at Nine Elms and Battersea could be open by 2020.

According to TFL, the extension will kick-start regeneration in the Nine Elms area, where Kieran Timberlake is currently overseeing the construction of the new US Embassy (pictured below), and ‘provide major transport benefits’.

Grimshaw’s appointment is subject to a 10-day standstill period. The practice refused to comment.

Kieran Timberlake US Embassy 5

The news of Grimshaw’s victory emerged as work began on dismantling Battersea Power Station’s four iconic chimneys, with the first to be taken down on the south west corner of the Grade II-listed landmark.

The 101m chimney is being demolished from the top downwards using a circular rig which ‘munches’ its way down the tower, collecting the debris and enabling it to either be re-used or conserved as part of the development’s legacy programme.

It is expected it will take five months to take apart the first chimney. Once the rebuilding process begins the chimneys will be rebuilt from the base up in 1.2m stages, using concrete and reinforcement.

Battersea Power Station chimney

 

  • 2 Comments

Readers' comments (2)

  • Re: "American Embassy" why has the American Embassy been allowed to build it's new building on an askew angle compared to the other buildings around it? I questioned it's architect and was told that if it was deliberately put on an "angle" "torque" otherwise it would have had a frontage facing the river! (I would have assumed that's what every building near the river would want)
    Plus the views from across the river would be enhanced if the Embassy was aligned with it's neighbours

    Unsuitable or offensive? Report this comment

  • I am still puzzled about why they are demolishing the original terracotta chimneys only to rebuild them in reinforced concrete, especially as I don't expect the new boilers will need anything so big.

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.