Fraser Brown Mackenna unwraps cor-ten clad classrooms

Fraser Brown Mackenna has completed this £1.2 million classroom block at Carshalton Boys Sports College, in South London

The new 775m2 building houses eight new classrooms and staff offices.

The scheme used a standardised 1,200m grid and modular components, allowing it to be built quickly.

Clad in cor-ten, the perforated skin protects the south-east façade from solar gains. It also provides a ‘secondary safety function’, protecting the building from the adjoining playground and basketball courts.

Fraser Brown Mackenna

The architect’s view

The interiors are flooded with natural light and make use of moveable partitions to allow for flexible and generous teaching spaces. Full-height internal windows looking onto the corridor improve lighting conditions and aid surveillance. Indications post-completion have shown the transparency of the space has already had a positive impact, improving student attentiveness and behaviour within a more mature working environment.

Fraser Brown Mackenna

Project data

Location Winchcombe Road, Charshalton, Surrey
Type of project education
Client Carshalton Boys Sports College
Architect Fraser Brown Mackenna
Landscape and planning consultants ADN Planning
M&E consultant  XCO2 Energy
Quantity surveyor Burnley Wilson Fish
Planning supervisor Burnley Wilson Fish
Main contractor Charter Construction PLC
Funding part funded through the Academy Capital Maintenance Grant
Tender date January 2013
Start on site date February 2013
Completion date September 2013
Contract duration 7 months
Gross internal floor area 775m²
Form of contract and/or procurement JCT Design and Build
Total cost £1,221,382

Previous story (AJ 13.11.12)

Planning win for Fraser Brown MacKenna cor-ten clad classrooms

Fraser Brown MacKenna has been granted planning permission for a new classroom block at Carshalton Boys Sports College, in London

The £1.25 million, single-storey scheme will replace an existing temporary building by providing eight new classrooms, alongside staff facilities.

The new building will be clad in mesh, with a combination of solid and perforated cor-ten steel and aluminium panels.

The cor-ten panels are perforated to protect the south east façade from excessive solar gains. It also provides a secondary safety function, protecting the building from the adjoining playground and basketball courts.

Fraser Brown Mackenna

Project data

Architects Fraser Brown MacKenna Architects
Location Surrey
Type of project New Mathematics Classroom Suite
Client Carshalton Boys Sports College
Funding Academy Capital Maintenance Fund Grant
Tender date September 2012
Start on site date January 2013
Contract duration 29 weeks
Gross internal floor area 850m2
Form of contract and/or procurement JCT Design & Build
Total cost £1.25million
Quantity surveyor Burnley Wilson Fish
Planning supervisor Burnley Wilson Fish
Annual CO2 emissions 13.7 tonnes CO2 per annum

Fraser Brown Mackenna

Have your say

You must sign in to make a comment.

Related Jobs

Sign in to see the latest jobs relevant to you!

The searchable digital buildings archive with drawings from more than 1,500 projects

AJ newsletters