D5 Architects completes Milton Keynes coach station

[First look + project data] These are the first photographs of D5 Architects’ now completed coach and bus station in Milton Keynes

The £2.35 million scheme off junction 14 of the M1 includes a park and ride facility and was opened just before Christmas 2010.

Project data

Architects: D5 Architects LLP pre and post contract 
Location: Milton Keynes
Type Of Project: Transportation 
Structural Engineers: 
Andrew Howard and Partners (AHP) post contract, WSP pre-contract
Project Architect: D5 Architects LLP 
Design Team:  Contract administrator - WSP
Client: Milton Keynes Council
Funding: Housing: Homes & Communities Agency (HCA)  
Start on site date: June 2009
Contract duration: 30 weeks plus tenant fit out. Operational December 2010
Gross internal floor area: 480m²
Form of contract and/or procurement: Design & Build, NEC3 Option A Priced Contract with Activity Schedule  
Total cost: 
£2.35 million      
M&e consultant: 
RF Blount & Sons (M), Wilson Electrical (E) post contract, WSP pre-contract 
Quantity surveyor: 
Arcadis
Planning supervisor: WSP
Lighting consultant: Cooper Lighting 
Main contractor:
 ROK
Annual co2 emissions: N/A

Have your say

You must sign in to make a comment.

Related Jobs

Sign in to see the latest jobs relevant to you!

The searchable digital buildings archive with drawings from more than 1,500 projects

AJ newsletters