AHMM submits Google HQ plans

[First look + plans] AHMM has submitted a reserved matters planning application for a new £650 million Google’s headquarters building in King’s Cross, London

Planned to open in late 2016, the 93,000m² development will house all of the search engine giant’s London staff – currently based in Victoria and Holborn – under one roof.

Submitted to local authority Camden Council, the project is the latest addition to Argent’s 27-hectare King’s Cross regeneration vision which won outline planning seven years ago.  

The mixed-use proposal ranges from seven to eleven storeys and features 68,000m² of office space and 4,600m² of retail.

Simon Allford, director of Allford Hall Monaghan Morris, said: ‘This building is underpinned by cutting edge design intelligence and technologies to provide a sophisticated twenty first century working environment for Google’s staff.

‘The architectural approach, which has taken inspiration from King’s Cross and St Pancras International railway stations, complements the local area’s strong industrial heritage and will be a building London can be proud of.’

Google UK’s managing director Dan Cobley said: ‘Building our new headquarters in King’s Cross is good for Google and good for London. We’re committed to the UK and to playing a role in the regeneration of this historic area.’

David Partridge, director of Argent King’s Cross, said: ‘This project is hugely important for King’s Cross and underlines our commitment to support world class design. It will attract further investment into the wider area and act as a catalyst for the local economy and the community which we are building.’

The one hectare project is planned to start on site in early 2014 subject to planning.

 

Project data

Architects: AHMM
Location: King’s Cross, London
Type Of Project: Headquarters
Structural Engineers: Watermans
Project Architect: AHMM
Design Team: Tbc
Client: Google
Funding: Private
Tender date: Tbc
Start on site date: Q1 2014
Contract duration: Occupation Q2 2016
Gross internal floor area: 1,000,000 sq ft
Form of contract and/or procurement: Two stage design and build
Total cost: £650 million
M&E consultant: Hilson Moran
Quantity surveyor: Davis Langdon
Planning supervisor: ECAL
Lighting consultant: GIA Equation
Main contractor: Tbc
Selected subcontractors and suppliers: Tbc
Annual co2 emissions: Tbc

 

 

 

 

 

 

 

 

Have your say

You must sign in to make a comment.

Related Jobs

Sign in to see the latest jobs relevant to you!

The searchable digital buildings archive with drawings from more than 1,500 projects

AJ newsletters