Cost analysis

Gross area: 6510m2

SUBSTRUCTURE

FOUNDATIONS/SLABS £123.38/m2

Mass concrete pad foundations; 600mm-diameter bored tension and compression piles ; central column supported on four 1800mm-diameter piles; end columns supported on two 1200mm-diameter piles; reinforced concrete slabs, retaining walls and columns to basement plant zone; cast-iron and clay drainage; precast concrete manholes, aco channels

SUPERSTRUCTURE

FRAME £308.41/m2

Central spine truss 'A' frame wishbone beam assemblies; truss-bearing nodes to in-situ columns; tie bars and end connectors; plate steel 'sheep's head' nodes; two 50m-long precambered tubular steel latticework roof trusses, mast and tie bars; fairfaced in-situ concrete and white acid-etched precast structure at ground level; hollow section steel framework to lift towers

UPPER FLOORS £221.62/m2

White cement precast concrete coffered slab units with acid-etched soffit; in-situ rc structural screed; 'T' section terrace units with acid-etched soffit

ROOF £158.49/m2

Cantilevered 'aerofoil' roof sections; clad with curved aluminium roof decking and curved powder-coated aluminium perforated soffit panels. Polyester powder-coated, curved pressed metal bullnose fascias; box gutter and galvanised steel open grille gutter gratings. Sarnafil fully bonded roofing membrane on insulation, steel decking to all flat roof areas

STAIRCASES £146.20/m2

Powder-coated mild steel balustrades to terraces; toughened glass, galvanised steel mesh and powder-coated infill panels; stainless steel handrails to vomitory openings; galvanised mild steel step treads to upper terrace isles; four hanging staircases with fabric awnings; footbridge link to Compton Stand; three single-flight stairs at ground level; plant room access stairs, platforms and ladders

EXTERNAL WALLS £110.20/m2

10mm frameless glass folding wall to hospitality box fronts; Alucabond rainscreen cladding; Luxcrete glass block walling; 12mm laminated opaque glass curtain walling; 190mm rendered blockwork; polyester powder-coated aluminium louvres

WINDOWS AND EXTERNAL DOORS £8.57/m2

Purpose-made fr30 profile metal doors with Pyroguard clear glazing; half- hour fire-resistant plywood-faced painted doors to ground-floor plant and wc areas ; stainless steel ironmongery; roller shutters to ground- floor bar areas

INTERNAL WALLS AND PARTITIONS £19.04/m2

Plasterboard partitions; one-hour fire-rated folding acoustic partition to president's and secretary's box; laminated wc cubicle partitions; laminated demountable duct access panelling; Durasteel fire separation wall to service risers

INTERNAL DOORS £12.14/m2

Half-hour fire-resistant plywood-faced painted doors with Pyran vision panels; stainless steel ironmongery

INTERNAL FINISHES

WALL FINISHES £7.35/m2

Plasterboard drylining, skim coat and paint finish

FLOOR FINISHES £15.49/m2

Epoxy screed to ground-floor wcs and bars; carpet tiles on screed to hospitality boxes; vinyl sheet flooring to level 2 and 3 corridors, wcs and bar areas; waterproof sealant to lower-tier terraces

CEILING FINISHES £12.40/m2

Metal tile suspended ceilings to lift lobbies, plasterboard and skim coat suspended ceiling to food preparation areas, purpose-made perforated aluminium services casings to corridors and ground-floor wcs

FITTINGS AND FURNISHINGS

FURNITURE 76.89/m2

Polypropylene external terrace seating; painted mdf servery units; purpose- made steel bars with seven vinyl-faced timber crockery stores ; Formica- faced bar fittings and counter tops; motorised fabric sun blinds to roof aerofoil and hospitality boxes

SERVICES

SANITARY APPLIANCES £3.92/m2

Ceramic wash hand basins, urinals; ceramic and stainless steel cleaners' sinks. Sanitary appliances also included in disposal installations

SERVICES EQUIPMENT £32.38/m2

Catering equipment; fittings to bar areas and dining rooms

DISPOSAL INSTALLATIONS £55.25/m2

Vacuum foul-water system including ceramic wc pans, stainless steel trough urinals and upvc pipework; soil, waste and vent installation; gravity drainage installation up to vacuum boxes; syphonic rainwater system

WATER INSTALLATIONS £24.91/m2

Hot, cold and drinking water installations; cold feeds to water heaters

SPACE HEATING & VENTILATION £12.10/m2

3kW Dimplex heat emitters to hospitality boxes; electric convector draught barrier heaters to dining-room restaurant. wc, kitchen, plant room and lift motor room extract system

ELECTRICAL SERVICES £41.55/m2

Site lv distribution, lv switchgear and distribution, lighting distribution, compact fluorescent light fittings, emergency lighting, small power, power supplies to lifts and mechanical plant

LIFT AND CONVEYOR INSTALLATIONS £17.78/m2

Three 8-person side-acting hydraulic passenger lifts

PROTECTIVE INSTALLATIONS £0.90/m2

Dry riser installation and lightning protection system

COMMUNICATIONS INSTALLATIONS £21.30/m2

Analogue addressable fire alarm system, PA system

SPECIAL INSTALLATIONS £3.38/m2

Safety lifeline system to roofs; demountable scaffold tower for access to aerofoil and box level blinds; safety platforms and guard rails; bosun's chair access system to main roof mast

BUILDER'S WORK IN CONNECTION £8.25/m2

PRELIMINARIES AND INSURANCES

PRELIMINARIES, OVERHEADS & PROFIT £160.77/m2

Management contractor's pre-construction fee, construction fee, staff costs and preliminaries

DEMOLITIONS

DEMOLITIONS £211,960

Demolition of existing Grand Stand

EXTERNAL WORKS

EXTERNAL WORKS £334,395

Pavings, access road, service ducts, removal and reinstatement of cricket pitch at boundary

GENERAL EXCLUSIONS

Third umpire camera, feature lighting, loose furniture, VAT, professional fees, prescribed fees etc, works contractor incentivisation payments

Cost summary

Cost per m2 Per cent

(£) of total

SUBSTRUCTURE 123.38 7.74

SUPERSTRUCTURE

Frame 308.41 19.35

Upper floors 221.62 13.91

Roof 158.49 9.94

Staircases 146.20 9.17

External walls 110.20 6.91

Windows and external doors 8.57 0.54 Internal walls and partitions 19.04 1.19

Internal doors 12.14 0.76

Group element total 984.67 61.77

INTERNAL FINISHES

Wall finishes 7.35 0.46

Floor finishes 15.49 0.97

Ceiling finishes 12.40 0.78

Group element total 35.25 2.21

FITTINGS AND FURNITURE 76.89 4.83

SERVICES

Sanitary appliances 3.92 0.25

Services equipment 32.38 2.03

Disposal installations 55.25 3.47

Water installations 24.91 1.56

Space heating and ventilation 12.10 0.76

Electrical services 41.55 2.61

Lift & conveyor installations 17.78 1.12

Protective installations 0.90 0.06

Communication installations 12.30 0.77

Special installations 3.38 0.21

Builder's work in connection 8.25 0.52

Group element total 212.72 13.36

PRELIMINARIES & INSURANCE 160.77 10.09

Total 1593.68 100.00

CREDITS

CLIENT

Marylebone Cricket Club

ARCHITECT

Nicholas Grimshaw and Partners: Jason Embley, Miriam Fitzpatrick, Nick Grimshaw, David Harriss (director in charge), Jim King, David Portman

QUANTITY SURVEYOR

Davis Langdon & Everest

STRUCTURAL ENGINEER

Ove Arup & Partners

MANAGEMENT CONTRACTOR

Heery International

PROJECT MANAGER gtms

CONTRACT TYPE

Management Contract

START DATE

September 1995

COMPLETION DATE

June 1998

CAPACITY

6000 seats

SUBCONTRACTORS AND SUPPLIERS

precast concrete Tarmac Precast, mechanical and electrical abb Steward, steel structure Watsons, phase 1 & phase 2 architectural metal Glazzards, phase 2 steel stairs Littlehampton Welding, aerofoil roof cmf, seating Restall, phase 1 bar roller shutters hvp, cladding WW Roofing & Cladding, lifts Oakland Elevators, feature lighting Equation Lighting, phase 2 fit- out Withney, dining-room glazing English Architectural Glazing, box glazed doors Dorma, glass blocks Luxcrete, wc cubicles Prospec, saftey access systems On Line Safety Access Systems, flat roofing Fenland (Sarna), roof truss & mast Watsons, vacuum drainage Servac, ironmongery Allgoods

Have your say

You must sign in to make a comment.

The searchable digital buildings archive with drawings from more than 1,500 projects

AJ newsletters