Costs

  • Comment

2Demolition of existing house and stable, rear extensions and garden walls with stone salvaged for reuse;

CCTV Survey: brick and blockwork Waldron Brickwork; stone renovation N Evans; scaffold Albion Hire Services; joinery Anton J Cave; concrete cutting UKDD; structural steel Reynolds & Litchfield; PCC floor Bison Concrete; slate roofing Cobsen Davis; asphalt tanking Nottingham Rock Asphalt; roof glazing Campion Glass; mansafe system The Access Group; structural glazing Glaswall; metal fascia & soffits PMF Roofcraft; patent glazing Campion Glass; colt windows Colt International;

windows Crittalls Windows; stairs Excel Engineering; balsutrade Excel Engineering; brise soleil Levolux; screed Telling Finshes;

lift Otis; fire stopping B-in-Line; stud partitions B-in-Line;

plastering Key Building Finishes; rainwater goods PMF Roofcraft;

suspended ceiling B & K Ceilings; MF ceiling B-in-Line; ceramic tiling Tellings Finishings; decoration Peveril Decorators; hardwood floor Beachams; vinyl & carpet Beachams; acoustic panels Black Cat Cost summary Cost analysis refers to gross internal floor area.

Costs based on tender sum Cost per m 2 Percentage DEMOLITIONS AND ALTERATIONS 81.27 4.2 SUBSTRUCTURE 87.08 SUPERSTRUCTURE Frame/unframed 21.64 steelwork Upper floors and stairs 77.28 4.0 External walls 111.85 5.9 External doors 33.15 1.7 and windows Roof 119.69 Internal walls 68.89 3.6 Internal doors 45.97 2.4 GROUP ELEMENT TOTAL 478.47 25.0 INTERNAL FINISHES Floor, wall and ceiling 134.02 7.1 finishes FITTINGS AND FURNISHINGS Fittings 7.75 Curtains, blinds and 116.14 6.2 furniture Sound-recording studios 77.4 4.1 (electronics) GROUP ELEMENT TOTAL 201.29 10.8 SERVICES M&E 269.95 Lift 29.38 GROUP ELEMENT TOTAL 299.33 15.8 EXTERNAL WORKS Paving 14.63 Drainage 10.66 Mains service 7.75 0.5 Acoustic works 116.14 6.1 GROUP ELEMENT TOTAL 149.16 8.0 PRELIMINARIES, 466.28 OVERHEADS AND PROFIT TOTAL (excluding VAT) 1,896.92 100

  • Comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.