Cost summary

Cost per m 2 Percentage

DEMOLITIONS AND ALTERATIONS 198 7.4

SUBSTRUCTURE 79 Frame 185 Upper floors 348 13.2 Roof 76 Staircases 48 External walls 49 1.8 Windows 68 External doors 7 0.3 Internal walls and partitions 52 2.0 Internal doors 73 2.8

GROUP ELEMENT TOTAL 906 34.3

INTERNAL FINISHES Wall finishes 56 2.1 Floor finishes 51 1.9 Ceiling finishes 23 0.8 Decorations 40

GROUP ELEMENT TOTAL 170 6.3

FITTINGS AND FURNISHING 66 2.5

THEATRE EQUIPMENT 133 5.0

SERVICES Sanitary appliances 16 0.6 Disposal installations 64 2.4 Water installations 21 0.8 Space heating and air treatment 174 6.5 Electrical services 174 6.5 Lift and conveyor installations 62 2.4 Protective installations 61 2.3 Communication installation 17 0.7 Builders' work in connection 9 0.4

GROUP ELEMENT TOTAL 598 22.6

EXTERNAL WORKS 6 0.2

PRELIMINARIES AND INSURANCE 358 13.5

GENERAL CONTINGENCY 138 5.2 TOTAL 2,652 100 Tender March 2004 Start on site May 2004 Contract duration 60 weeks Gross internal floor area 854 m 2Form of contract JCT98 without quantities Total cost £2,265,000 Client Theatre Royal Bath Client representative Bishopston Architect Haworth Tompkins: Tom Grieve, Will Mesher, Steve Tompkins, Roger Watts Structural engineer Buro Happold Services engineer Buro Happold Quantity surveyor Buro Happold Theatre consultant Anne Minors Performance Consultants Acoustic consultant Fleming & Barron Planning supervisor Buro Happold Access consultant Buro Happold Lighting consultant Patrick Woodroffe Lighting Design Main contractor Emerys of Bath Subcontractors and suppliers Mechanical & electrical subcontractor Stourtons; structural steelwork and architectural metalwork Robbin Engineering; theatre technical Stage Electrics; theatre seats and staging Steeldeck; joinery Falcon Joinery; zinc roofing Boss Metals; traditional roofing Young Roofing; concrete RC Formwork; glazing (window system) Velfac;

glazing (other) Roman Glass; resin floor Ryebrook Resin; soft floor finishes N&S Flooring; intumescent painting A Bagnall & Son; profiled metal deck Prodeck Fixing; decorations E J Mannings; waterproofing Sika; scaffolding Cole Scaffold; passenger lift Triangle Lift Services; platform lift Elephante; sprung floor CDM