Cutty Sark Gardens Tender

The Cutty Sark Gardens Brief is currently being tendered by LB Greenwich through an open single stage tender process.

The project presents a very exciting opportunity to be involved in the design and phased reconstruction of one of London's highest profile public spaces. With it's prominent riverfront location, the World Heritage Site currently serves nine million visitors annually. The Cutty Sark will reopen in 2010, and in 2012 Greenwich will be hosting key Olympic events - factors which will further increase visitor numbers. The ambition of the project is to create a world class public space, and as such a talented and innovative design team is being sought to deliver this vision. The winning team will be responsible for delivering the £2.4million project from RIBA work stages C to E.

The project is being led by LB Greenwich (contact details of overseeing officer, Mike Neil are included below) with Design for London forming part of the selection panel.

Full details of the tender are available on LB Greenwich’s website via this link:

Programme:

Tenders are to be returned by 12.00 noon on Friday 6th February 2009
Stage C outline scheme -End March 2009
Stage E detailed design -November 2009
Planning etc. consents submitted -November 2009

Key contact:

Mike Neill
Project Manager
LB Greenwich